All the upgrades we chose came to almost $12k! Mind you this is for like 80 light fittings (not even the downlights just yet! We're fitting those afterwards), heaps of dimmers, 2-ways, extra circuits, outdoor lighting etc. One thing that I cant wait to see is the upgraded faceplates we chose for some of the main light switches! They are the Clipsal Saturns with LED rings. They pretty much have a ring of light when they aren't on so you can see them which turns off when the light is on. You can set this to turn on when the light is on as well and are really futuristic type upgrade :)


After we finalised our electricals we finally received our Post Contract Variation. This was astonishing. Depsite all of our "little" changes it only came in at $2700! We were expecting close to $10k so we finally had the first bit of good news - financially - so far! In light of this sudden stroke of luck with Plantation we have decided to upgrade the Kitchen Bench to 40mm with waterfall edges on boths sides hehe. How can we resist now! So unless this costs $7k or less we will be happy :)
Still waiting for council approval in the meantime - Plantation use a private certifier which SHOULD make things quicker but it doesn't. Plus its impossible to get updates from the certifier in the meantime. Recently we were also given a timeline as to what happens after get approval and it can still be a few months before we even have a start date!! Needless to say that didn't go down to well, but hopefully it wont come to that.